REQUIREMENTS
- Duly accomplished Prescribed Application Forms
- Barangay Clearance for Construction (with Cedula) (1 Original, 3 Photocopies)
- Clearance for Construction from Homeowners’ Association, if any (1 Original, 3 Photocopies)
- Fire Safety Evaluation Clearance
- Zoning Certificate/ Clearance for Construction
- PLO Certificate (Power Line Operator Certificate)
- In case the applicant is the registered owner of the lot: (1 Original, 3 Photocopies)
- Certified True Copy of TCT/ OCT
- Certified True Copy of Tax Declaration
- Photocopy of Current Real Property Tax Receipt
- In case the applicant is not the registered owner of the lot, submit a photocopy of a duly notarized Contract of Lease or Deed of Absolute Sale (4 Photocopies) Award Notice or Notarized SPA
- If the TCT is under CLOA (agricultural land), awarded by DAR, please submit DAR and MARPO Clearance(1 Original, 3 Photocopies)
- Five (5) sets each of the following Ancillary Plans and Documents signed and sealed over the printed name of the duly licensed and registered professionals.
- Geodetic Documents (Lot Plan)
- Bill of materials and Cost Estimates
- Specifications
- Architectural Plan
- Civil/ Structural Plan
- Electrical Plan
- Sanitary Plan
- Plumbing Plan
- Mechanical Plan, if necessary
- Electronics Plan, if necessary
- 3 Photocopies of PRC ID and PTR of Duly Registered Professionals who signed the plans and documents, with original signed and sealed
- DPWH Clearance for projects along National Road and designated waterways within local jurisdiction where the project is sited
- DOLE approved Construction Health and Safety Program
- Additional for Plumbing Plan:
- NOTES FOR SEPTIC TANK CONSTRUCTION AND PLAN
- Three (3) chambers
- Three (3) manholes (MH) and Three (3) Cleanouts (CO) each chamber shall have its own MH and CO
- All reinforced concrete flooring
- Minimum of 1.20 meters liquid depth
- Minimum of .20 meter deep for air space
- NOTES FOR SEPTIC TANK CONSTRUCTION AND PLAN
- Additional for Civil/ Structural Plan:
- FOR BUILDING HAVING TWO (2) STOREYS OR MORE
- Submit 3 Copies of Structural Analysis Computation (Signed and Sealed)
- FOR BUILDING HAVING TWO (3) STOREYS OR MORE
- Submit 2 Copies of Soil Boring Test – Geotechnical Report (signed and sealed)
- FOR BUILDING HAVING TWO (2) STOREYS OR MORE
- Additional for Electrical Plan:
- AS PER R.A. 7920, ART. 4, SEC. 31
- Submit 3 Copies of Electrical Design Analysis (Signed and Sealed)
- AS PER R.A. 7920, ART. 4, SEC. 31
STEPS
- Submit the necessary requirements for the application of a Building Permit with duly accomplished Building Permit Form
- Receipt of payment
- Proceed to the Cashier at Office of the Municipal Treasurer for corresponding fee
- Present Official Receipt to the Municipal Engineer and wait for the release of the permit